经对我市16个高层37栋共48.66万m~2与5个小区(2个工业区3个住宅区)共98.16万m~2的初步调查,建筑工期情况如下: 一、高层建筑工期 高层建筑工期一般由三个阶段组成,第一个阶段是基础打桩工程,由专业队伍承建,根据地质情况,一般需要总工期的10%,即两到三个月完成第二阶段结构与粗装饰由一家承建,约占总工期的
After a preliminary investigation of a total of 981,600 m2 of 37 high-rise buildings in the city’s 16 high-rise buildings (48,660 m2) and five communities (two industrial areas, three residential areas), the construction period is as follows: 1. High-rise building construction period The construction period is generally composed of three stages. The first stage is the foundation piling project, which is constructed by a professional team. According to the geological conditions, it usually takes 10% of the total construction period, that is, two to three months to complete the second stage structure and rough decoration. One contractor, about the total duration