鄄城段今春修堤任务很重,绝大部分人员都投入了修堤工程。参加整险工程的只有工程队长一人,年近五十的老班长二人,二年黄河工龄的新工人四人,另配临时工七人及部分民工。就在这样的情况下,自三月九日至四月九日,仍然胜利完成了苏泗庄、营坊、桑庄三处整险工程。实用人工,仅占计划人工一千零二十个工日的百分之三十九点六六,提前完成了整险任务,工程质量也全部合格。
Juancheng dike renovation project in spring is very heavy, the vast majority of personnel have put into repair dike project. Only one engineering captain to participate in the entire insurance project, nearly two decades of the new squad leader, two new workers in the Yellow River two years of work four, with temporary workers and some of the other migrant workers. Under such circumstances, the three intact projects of Su Si Zhuang, Ying Fang and Sang Zhuang were still successfully completed from March 9 to April 9. Practical labor accounted for only 39.66% of the planned one-thousand and twenty workers’ days, completing the whole-risk assignment ahead of schedule and all the projects were qualified.