在地铁工程施工中,经常使用冻结技术进行土体加固,如盾构始发、接收端头井加固、盾构推进区间障碍物的清除、地铁车站或区间的修复等工程。加固完成之后,为不影响后续工序的施工,需将冻结加固时用的冻结管拔出,恢复原有地层工况,但在拔管施工中经常会发生冻结管拔断、拔不动等情况,严重影响冻结施工效果。笔者多年从事冻结拔管施工,总结出一套切实可行的冻结拔管施工技术。
In the subway construction, often using frozen technology for soil reinforcement, such as shield the beginning of the receiving end of the shaft reinforcement, removal of obstacles in the shield to promote clearance, metro station or section of the repair and other projects. After the reinforcement is completed, in order not to affect the construction of subsequent processes, the frozen pipe used for freezing and reinforcement needs to be pulled out to restore the original working conditions. However, often the freezing pipe is unplugged and unplugged during the extubation construction , Seriously affecting the freezing effect of construction. The author for many years engaged in the construction of frozen extubation, summed up a set of practical technology of frozen extubation.