论文部分内容阅读
预制钢筋混凝土柱(梁)的底模传统作法多为在夯实的素土上坐浆墁砖抹水泥砂浆面层,不仅工期长,而且多用技术工人,很不经济。我们在实践中采用了多节架空底模分段脱模技术,取得了良好的效果。施工方法:柱(梁)模板设计→放线抄平→
The traditional practice of prefabricated reinforced concrete pillars (beams) is to use mortar and mortar to lay cement mortar on the compacted plain soil. It not only has a long construction period, but also uses skilled workers. It is uneconomical. In practice, we adopted a multi-section overhead sub-section demoulding technology and achieved good results. Construction method: column (beam) template design → take-off line copying →