1994年,在以打开四个卡口为重点的治淮攻坚战中,淮委东调南下直属工程指挥部,直接负责大官庄枢纽、韩庄运河省界段两个卡口工程的建设。这个指挥部深知肩负的责任重大,一年多来兢兢业业,刻苦攻关,工程的建设管理卓有成效,基本实现了年初预定的工程建设目标。 指挥部十分明确工程建设管理的主要任务。在协调地方关系上,不仅指挥部一班人四处奔波,还积极依靠淮委力量,必要时请有关领导和部门出面协调,使工程的开展有了一个好的建设环境。
In 1994, in the crucial battle of tackling the Huai-Huai invasion with the opening of four bayonets, the Huai-Wei East transferred the command project directly under the South to directly under the command of the two bayou projects at Dachangzhuang hub and Hanzhuang canal. The headquarters was fully aware of the great responsibility it shouldered. After more than a year of hard work and painstaking studies, the construction management of the project was fruitful and the goal of the construction scheduled for the beginning of this year was basically achieved. Command is very clear that the main task of construction management. In coordinating local relations, not only are the leaders of a command group running around, but also actively relying on the strength of the Huai Committee and, if necessary, inviting the relevant leaders and departments to come forward for coordination so that the construction of the project has a good environment for construction.