在火力发电厂的安装工作中保温工程约占总建安工作量的1/4。但由于此项工程技术性较差、施工条件简陋、艰苦、在经营管理上往往得不到大家的重视。造成很大的浪费,在当前的双增双节运动中,特别需要引起重视。现以20万kW机组为例,需用保温耐火材料约6000m~3。火车运输每节车箱装60m~3,就需要100节车箱。这么大的量,从采购、运
In the installation of thermal power plants, the thermal insulation project accounts for about 1/4 of the total construction safety. However, due to the poor technical quality of the project, the construction conditions are simple, hard, and often do not get everyone’s attention in the management. It causes great waste. In the current double-increasing double-sports campaign, special attention is needed. Taking 200,000 kW units as an example, it is necessary to use insulation and refractories about 6000m~3. Each train box is loaded with 60m~3 trains, it needs 100 carriages. Such a large amount, from the procurement and transportation