成组更换道岔的施工方法有成组预铺横移法、成组纵向移动法和分股更换法。由于受场地限制,在大多数施工中,都是结合前两种方法。现将成组更换道岔施工组织介绍如下:1施工前期调查、准备1.1施工计划的提报,日班计划下达。1.2挖探、调查、排障。施工前会同电务、供电、通信、车务等设备管理单位联合调查确定施工可能影响的线缆走向并进行标记,确定处置及
The construction methods for changing turnouts in groups are as follows: group prefabrication and transverse moving method, group longitudinal moving method and sub-share replacement method. Due to site constraints, in most constructions, the first two methods are combined. Now the group to replace the turnout construction organization is as follows: 1Pre-construction survey, preparation 1.1The construction plan report, day plan issued. 1.2 digging, investigation, troubleshooting. Before construction, joint investigation will be conducted with equipment management units such as electricity service, power supply, communications and vehicle service to identify and mark the likely impact of the construction on the cable and to determine the disposal and /