本刊讯12月10日,青岛市政府组织召开了济青高铁和青连铁路征地拆迁推进会议,青岛市政府副秘书长张新竹主持会议。济青高速铁路有限公司副总经理周宪东介绍了济青高铁工程进展情况,从通车要求和完成投资任务两个方面强调了济青高铁青岛段征地拆迁工作的紧迫性和必要性,建议青岛市今年12月底完成控制性工程征地工作,2016年2月底全部完成地上附着物清表工作,6月底全部完成
On December 10, the Qingdao Municipal Government organized the promotion meeting of Jinan-Qingdao High Speed Rail and Qinglian Railway to land acquisition and demolition, and Zhang Hsinchu, deputy secretary-general of Qingdao Municipal Government, presided over the meeting. ZHOU Xian-Dong, Deputy General Manager of Jinan-Qingdao High Speed Railway Co., Ltd., introduced the progress of Jinan-Qingdao High Speed Rail Project and emphasized the urgency and necessity of land acquisition and demolition in Qingdao section of Jinan-Qinghai-Tibet High-speed Railway from the two aspects of opening and completion of investment tasks. The end of December to complete the control project of land acquisition, by the end of February 2016 to complete the surface attachments clear work, completed by the end of June