论文部分内容阅读
大埔县百侯电站橡胶坝工程,在有关部门的协作下,于今年11月8日建成并通过验收,正式投入使用.这是目前省内单跨最长的橡胶坝.这个县的百侯电站,座落大埔境内梅潭河中游,装机容量3×800千瓦.原设计水头12米,实际10.5米,达不到额定出力.最近安装使用橡胶坝后试机,平均每台机组增加100千瓦左右,实现了满发,取得了显著的经济效益.
The construction of Baoba Hydropower Station rubber dam project in Dapu County was completed and passed the inspection and acceptance on November 8, 2008. This is the longest rubber dam in the province with the single stride. The power station is located in the middle reaches of Meitai River in Tai Po with an installed capacity of 3 × 800 kilowatts. The original design head of 12 meters, the actual 10.5 meters, less than the rated output. Recently installed rubber dam test machine, an average increase of 100 units Kilowatts or so, achieved full, made significant economic benefits.