我区从一九六八年开始修建沥青路面,截止目前全区共有沥青路面1350公里,近几年黑色路面,不仅在数量上增长较快,工程质量和建设标准方面也逐步提高,前几年修建的大都是路拌(冷拌)沥青(渣油)表处路面,另有少部分沥青贯入式路面。一九七四年我段试制了半固定式沥青砼拌和机后,开始采用机械热拌热铺方法施工修建了部分沥青砼路面。自一九七四年冬季试机起,四年来平度、益都两县在潍坊至石岛、王村至潍坊公路上
Since 1968, our district started to construct asphalt pavement. Up to now, there are 1350 kilometers of asphalt pavement in the whole region. In recent years, the black pavement has not only increased rapidly in quantity, but also gradually improved in terms of project quality and construction standards. A few years ago, Mostly built road mix (cold mix) asphalt (residue) surface at the table, while a small part of the asphalt into the road. In 1974, after the trial manufacture of semi-fixed asphalt concrete mixer, we began to construct a part of asphalt concrete pavement by means of mechanical hot-mix hot-laying method. Since the pilot test in the winter of 1974, four years ago, both Pingdu County and Yidu County took the road from Weifang to Shidao and Wangcun to Weifang