葛洲坝工程自1981年胜利实现了大江截流、二江发电、三江通航后,到1983年底,一期工程已全部建成,经过验收,正式投入运用。这是一件值得庆贺的大事。葛洲坝工程是我国在长江干流上修建的第一座大型水利枢纽工程,其工程规模和技术复杂程度都超过了我国水利水电建设曾经达到的水平。开工以来,在党中央,国务院的领导和关怀下,
Since the Gezhouba Project had achieved great river closure, the production of the Erjiang power, and the navigation of the Sanjiang River in 1981, by the end of 1983, the first phase of the project had been completed, and it was formally put into operation after acceptance. This is a great event to celebrate. The Gezhouba Project is the first large-scale water control project built on the mainstream of the Yangtze River in China. Its engineering scale and technical complexity exceed the level reached by China’s water conservancy and hydropower construction. Since the start of the work, under the leadership and care of the Central Party Committee and the State Council,