1框玻璃幕墙的施工工艺流程框玻璃幕墙的施工工艺主要有以下过程:施工准备→测量放线→预埋件处理→连接角码安装→立柱安装→横梁安装→横梁、立柱的调整与紧固结构→安装托条→安装玻璃→幕墙收口→伸缩缝处理→清洁检查→竣工验收1.1测量放线先将主体结构上的预埋件表面清理干净,然后根据建筑物轴线弹出纵横两个方向的基准线和标高控制线。
1 frame glass curtain wall construction process flow frame Glass curtain wall construction process mainly in the following process: Construction Preparation → measurement pay-off → embedded parts processing → connection angle code installation → column installation → beam installation → beams, column adjustment and fastening Structure → mounting bracket → installation of glass → curtain wall closing → expansion joints → cleaning inspection → completion and acceptance 1.1 measurement of the first line of the main structure of the embedded parts surface clean, and then according to the vertical axis of the building pop-up in both directions Line and elevation control line.