论文部分内容阅读
专家们对布拉茨克水电站水工建筑物进行了调查,在此基础上研究了水电站管理方面的一些问题。首先是在出现老化迹象的条件下保持建筑物的工作能力、可靠性和耐久性;其次是河床坝上游面下方岩石与混凝土接触情况,并对坝段位移、变形、渗漏及动荷载等情况进行监测及分析,得出结论:布拉茨克水利枢纽建筑物能适应其周围环境,老化迹象不明显,稳定性良好,但有必要制定有效监测动荷载的监控计划。
The experts conducted a survey on the hydraulic structures of the Bratsk hydropower station and on this basis studied some issues concerning the management of hydropower stations. The first is to maintain the building’s working ability, reliability and durability under the condition of signs of aging. The second is the contact between rock and concrete under the upstream surface of the river bed dam. The displacement, deformation, leakage and dynamic load of the dam And concluded that Bratsk hydropower station buildings can adapt to their surroundings, the signs of aging are not obvious, and the stability is good. However, it is necessary to develop a monitoring plan to effectively monitor dynamic loads.