宝钢二高炉点火试生产一年来,设备运行正常,生产稳步上升,主要生产技术经济指标达到了设计要求。试生产的情况说明:以国内为主自行设计、制造和建设的大型现代化高炉是成功的,这是参加设计、制造、施工、生产的职工团结协作、共同努力的结果。 一、设备承包工作的主要成绩 宝钢二号高炉容积为4063m~3,是具有当前国际先进技术水平的现代化大型高炉,在国内是第一次设计制造这样现代化大型高炉。宝钢二高炉跟踪世界先进技术水平,
During the one-year trial production of Baosteel II blast furnace, the equipment was in normal operation and production rose steadily. The technical and economic indexes of the main production reached the design requirements. Trial Production Description: Large-scale modern blast furnaces designed, manufactured and built domestically are successful. This is the result of concerted efforts and joint efforts by staff and workers involved in the design, manufacture, construction and production. I. Major achievements of equipment contracting Baosteel II blast furnace volume is 4063m ~ 3, which is the modern large-scale blast furnace with the current international advanced technology level. It is the first time to design and manufacture such a modern large-scale blast furnace in China. Baosteel II blast furnace to track the world’s advanced technology,