摘要:静压预应力桩基础作为一种新基础类型,由于其施工具有低噪声、无振动、污染小、施工快等优点,因而广泛应用于多层、高层建筑工程中。由淤泥、淤泥质土、水下沉积的饱和软粘土为主组成的软土在我国南方有广泛分布。软土承载力低,在软土地质上静压管桩施工要保证工程的施工质量,必须采取正确的施工方法和进行质量控制。
关键词:静压管桩;施工方法; 质量控制
Abstract: static prestressed pile foundation as a new foundation types, because its construction has no vibration, low noise and low pollution, construction fast etc, and thus widely used in multilayer, high-rise building project. By silt, and muddy soil, underwater deposition of saturated soft clay mainly comprised of soft soil in south China have widely distributed. Soft soil low bearing capacity, in soft soil mass static pressure pipe pile on construction to ensure the quality of construction projects, must take the correct construction method and quality control.
Keywords: static pressure pipe; Construction method; Quality control
中图分类号:TV523 文献标识码:A文章编号:
0 前 言
静压预应力桩基础作为一种新基础类型,通过静压把高强度的预应力管桩挤入土层,预应力管桩依靠和土层的摩擦力通过调整桩的长度来满足荷载的需要,达到保证建筑物的稳定。由于管桩通过工厂大批预制,承载力高、穿透力强、容易检测、工程造价低。静压管桩施工具有低噪声、无振动、污染小、施工快等优点,因此逐渐为建设单位、施工单位和设计部门所采用。
由淤泥、淤泥质土、水下沉积的饱和软粘土为主组成的软土在我国南方有广泛分布,这些土都具有天然含水量高、孔隙比大、透水性差、压缩性高、承载力低等特点。因此,在软土地质上静压管桩施工要保证工程的施工质量,必须采取正确的施工方法和进行质量控制。结合我们在工程的施工实践,谈谈自己的做法,供广大施工同行参考。
1 软土地基静压管桩的施工原理
1、静压管桩施工原理
静压管桩是通过压桩机液压传力机构,用压力机自重和机架上的配重提供压力施压于桩身上将桩压入土中的沉桩方法。静压管桩沉桩过程中,造成桩尖下原状土的初应力状态受到破坏,土体对桩尖产生相应的阻力,随着桩贯入压力的增大,当桩尖处土体所受压力超过其抗剪强度时,土体发生急剧变化而破坏,桩尖下土体被向下和侧向压缩挤开。同时,由于桩体的下沉,桩侧土体在压力的作用下产生塑性流动(粘性土)或挤密侧移和拖带下沉(砂性土),桩身受到土体强大的法向抗力所引起的桩周摩擦力的抵抗。当桩顶的静压力大于沉桩时的这些抵抗阻力时桩将继续贯入下沉。
2、预防桩机下沉的工艺原理
静压管桩施工前,我们根据软土地基的实际情况,对施工场地进行处理。一般情况下,我们采用对地基表面整平后进行压实,然后垫30cm—50cm的塘渣或建筑垃圾垫层,并分层进行碾压。碾压后的地基作为桩机的持力层,其承载力应大于桩机接地部分压强的1.2倍。其工艺原理为:当桩机荷载作用于垫层后,垫层在把荷载传给软土层的过程中向四周有一个扩散角。软土需要的受力面积可通过调整垫层的厚度来获得。扩散角的大小根据垫层所用材料的不同而不同。对碎石、灰土的扩散角在200—300左右。桩机荷载通过垫层传给软土层,垫层的厚度根据作用在垫层底面处土的自重压力与附加压力之和不大于软土的承载力特征值确定,即应符合式4.0.3—1要求。
Pcz+Pz≤faz (4.0.3—1)
式中:Pcz——垫层底面处土的自重压力(KN/m2);
Pz——垫层底面处的附加压力值(KN/m2);
faz——垫层底面处土层的地基承载力特征值(KN/m2);
由于我们采用场地全部进行处理,垫层的宽度不需计算。我们仅需计算出垫层厚度以满足软土需要的受力面积,达到软土层不被破坏,保证静压管桩施工中不会出现桩机下沉的目的。
2 软土地基静压管桩的施工
2.1施工工艺流程见图3.1—1
图3.1—1施工工艺流程
2.2 操作要点
2.2.1地基处理
1、场地清理整平
在进行桩基施工前,应对场地进行平整碾压。场地要求:现场的坡度应小于1/100,当桩位处的地面有混凝土地坪及旧有建筑物基础应予凿除。桩机最小工作半径:桩位中心距周边建(构)筑物应大于1/2压桩机宽度+1.0m,且对建(构)筑物应有保护措施。
2、垫层施工
施工前,应根据软土地基的承载力大小、桩机的接地压强和垫层材料的传力扩散角大小,通过施工计算确定垫层的设计厚度。
2.2.2测量定位
测量定位前要认真复核设计图纸及设计单位交桩点位,将坐标控制点、水准控制点按标准设置要求布设在施工现场。将轴线控制点引出6m—8m,做好测量控制网。根据设计图纸计算出各桩位坐标,根据基准点对桩位进行精确测放,桩位可打短钢筋并洒白灰进行标识。桩位测量允许偏差值为:单桩10mm,群桩20mm。
2.2.3 桩机就位
桩机就位前应进行检验,确保桩机的正常运行。桩机通过自身的行走系统移动到压桩位置,将桩机调平,并使其夹持器的中心對正桩位中心。
2.2.4 管桩就位
用桩机上的吊车吊起就近的管桩,管桩在插入桩机的夹持箱内时,压桩机上的司机应配合打开夹持箱的夹口,指挥员指令吊车慢慢把管桩放入夹持箱内。当管桩下放至地面10cm处停住,夹持器把管桩夹紧,吊车的吊钩放松。
管桩对中方法:管桩就位前,在桩位中心打上短钢筋,根据桩径的大小用放线设备放出相同半径的白灰线。管桩就位时,使管桩周边与白灰线对齐。
2.2.5 压桩
1、压好第一节桩是保证整根压桩的质量关键,定位和垂直度应严格控制。压入时,先应根据机上水平仪调平机台,同时须在桩机的正面和侧面分别设经纬仪或吊线锤,监控下桩垂直度,桩身垂直度偏差不宜大于0.5%。若桩身垂直度偏大,须拔出已压入部分,并根据经纬仪指示调整机台水平度使桩身垂直,同时记录此时机上水平仪的偏差量作为下次调平的修正值,再行压入,并认真注意压桩时的桩身和压力表的变化情况,如有异常偏移或倾斜立即分析原因,并采取校正措施,在确认压入方向无异常时,方可继续施压。
2、应合理调配管节长度,尽量避免接桩时桩尖处于或接近持力层,管桩接头数不宜超过4个,同一承台桩的接头位置应相互错开。
关键词:静压管桩;施工方法; 质量控制
Abstract: static prestressed pile foundation as a new foundation types, because its construction has no vibration, low noise and low pollution, construction fast etc, and thus widely used in multilayer, high-rise building project. By silt, and muddy soil, underwater deposition of saturated soft clay mainly comprised of soft soil in south China have widely distributed. Soft soil low bearing capacity, in soft soil mass static pressure pipe pile on construction to ensure the quality of construction projects, must take the correct construction method and quality control.
Keywords: static pressure pipe; Construction method; Quality control
中图分类号:TV523 文献标识码:A文章编号:
0 前 言
静压预应力桩基础作为一种新基础类型,通过静压把高强度的预应力管桩挤入土层,预应力管桩依靠和土层的摩擦力通过调整桩的长度来满足荷载的需要,达到保证建筑物的稳定。由于管桩通过工厂大批预制,承载力高、穿透力强、容易检测、工程造价低。静压管桩施工具有低噪声、无振动、污染小、施工快等优点,因此逐渐为建设单位、施工单位和设计部门所采用。
由淤泥、淤泥质土、水下沉积的饱和软粘土为主组成的软土在我国南方有广泛分布,这些土都具有天然含水量高、孔隙比大、透水性差、压缩性高、承载力低等特点。因此,在软土地质上静压管桩施工要保证工程的施工质量,必须采取正确的施工方法和进行质量控制。结合我们在工程的施工实践,谈谈自己的做法,供广大施工同行参考。
1 软土地基静压管桩的施工原理
1、静压管桩施工原理
静压管桩是通过压桩机液压传力机构,用压力机自重和机架上的配重提供压力施压于桩身上将桩压入土中的沉桩方法。静压管桩沉桩过程中,造成桩尖下原状土的初应力状态受到破坏,土体对桩尖产生相应的阻力,随着桩贯入压力的增大,当桩尖处土体所受压力超过其抗剪强度时,土体发生急剧变化而破坏,桩尖下土体被向下和侧向压缩挤开。同时,由于桩体的下沉,桩侧土体在压力的作用下产生塑性流动(粘性土)或挤密侧移和拖带下沉(砂性土),桩身受到土体强大的法向抗力所引起的桩周摩擦力的抵抗。当桩顶的静压力大于沉桩时的这些抵抗阻力时桩将继续贯入下沉。
2、预防桩机下沉的工艺原理
静压管桩施工前,我们根据软土地基的实际情况,对施工场地进行处理。一般情况下,我们采用对地基表面整平后进行压实,然后垫30cm—50cm的塘渣或建筑垃圾垫层,并分层进行碾压。碾压后的地基作为桩机的持力层,其承载力应大于桩机接地部分压强的1.2倍。其工艺原理为:当桩机荷载作用于垫层后,垫层在把荷载传给软土层的过程中向四周有一个扩散角。软土需要的受力面积可通过调整垫层的厚度来获得。扩散角的大小根据垫层所用材料的不同而不同。对碎石、灰土的扩散角在200—300左右。桩机荷载通过垫层传给软土层,垫层的厚度根据作用在垫层底面处土的自重压力与附加压力之和不大于软土的承载力特征值确定,即应符合式4.0.3—1要求。
Pcz+Pz≤faz (4.0.3—1)
式中:Pcz——垫层底面处土的自重压力(KN/m2);
Pz——垫层底面处的附加压力值(KN/m2);
faz——垫层底面处土层的地基承载力特征值(KN/m2);
由于我们采用场地全部进行处理,垫层的宽度不需计算。我们仅需计算出垫层厚度以满足软土需要的受力面积,达到软土层不被破坏,保证静压管桩施工中不会出现桩机下沉的目的。
2 软土地基静压管桩的施工
2.1施工工艺流程见图3.1—1
图3.1—1施工工艺流程
2.2 操作要点
2.2.1地基处理
1、场地清理整平
在进行桩基施工前,应对场地进行平整碾压。场地要求:现场的坡度应小于1/100,当桩位处的地面有混凝土地坪及旧有建筑物基础应予凿除。桩机最小工作半径:桩位中心距周边建(构)筑物应大于1/2压桩机宽度+1.0m,且对建(构)筑物应有保护措施。
2、垫层施工
施工前,应根据软土地基的承载力大小、桩机的接地压强和垫层材料的传力扩散角大小,通过施工计算确定垫层的设计厚度。
2.2.2测量定位
测量定位前要认真复核设计图纸及设计单位交桩点位,将坐标控制点、水准控制点按标准设置要求布设在施工现场。将轴线控制点引出6m—8m,做好测量控制网。根据设计图纸计算出各桩位坐标,根据基准点对桩位进行精确测放,桩位可打短钢筋并洒白灰进行标识。桩位测量允许偏差值为:单桩10mm,群桩20mm。
2.2.3 桩机就位
桩机就位前应进行检验,确保桩机的正常运行。桩机通过自身的行走系统移动到压桩位置,将桩机调平,并使其夹持器的中心對正桩位中心。
2.2.4 管桩就位
用桩机上的吊车吊起就近的管桩,管桩在插入桩机的夹持箱内时,压桩机上的司机应配合打开夹持箱的夹口,指挥员指令吊车慢慢把管桩放入夹持箱内。当管桩下放至地面10cm处停住,夹持器把管桩夹紧,吊车的吊钩放松。
管桩对中方法:管桩就位前,在桩位中心打上短钢筋,根据桩径的大小用放线设备放出相同半径的白灰线。管桩就位时,使管桩周边与白灰线对齐。
2.2.5 压桩
1、压好第一节桩是保证整根压桩的质量关键,定位和垂直度应严格控制。压入时,先应根据机上水平仪调平机台,同时须在桩机的正面和侧面分别设经纬仪或吊线锤,监控下桩垂直度,桩身垂直度偏差不宜大于0.5%。若桩身垂直度偏大,须拔出已压入部分,并根据经纬仪指示调整机台水平度使桩身垂直,同时记录此时机上水平仪的偏差量作为下次调平的修正值,再行压入,并认真注意压桩时的桩身和压力表的变化情况,如有异常偏移或倾斜立即分析原因,并采取校正措施,在确认压入方向无异常时,方可继续施压。
2、应合理调配管节长度,尽量避免接桩时桩尖处于或接近持力层,管桩接头数不宜超过4个,同一承台桩的接头位置应相互错开。