法国大屋(Grand Maison)抽水蓄能电站是一座常规水电结合抽水蓄能的混合式水电站,最大净水头为955米,为世界上特高水头的水电站。常规水电站装有四台150MW的冲击式水轮机;蓄能电站装有8台150MW混流式可逆机组。电站总装机容量为1800MW,分成两个厂房,常规电厂设在地面,蓄能厂房设在常规厂房地底下,上、下
The Grand Maison Pumped Storage Power Station is a conventional hydropower combined pumped storage hybrid power station with a maximum head of 955 meters and the world’s top-of-the-range hydroelectric power station. The conventional hydropower station is equipped with four 150MW impulse turbines; the accumulator station is equipped with eight 150MW Francis reversing units. The total installed capacity of the power plant is 1800MW, which is divided into two plants, the conventional power plant is located on the ground, the power plant is located under the underground of the conventional plant,