网络技术是一种科学的计划管理方法。在繁杂的工程中,使用这种方法可以抓住工程的主要矛盾线——关键路线,在缩短工期、提高工效、降低成本等方面均有显著效果。本文对某电厂二期工程综合控制进度,用网络技术进行了绘制。原横道计划安排土方开挖至三号机组投产,总工期为824天(即27个月),采用网络技术中的搭接网络计划,将主厂房吊装工程和锅炉吊装进行搭接施工,总工期只需752天(即24.7个月)。
Network technology is a scientific plan management method. In a complicated project, using this method can capture the key contradiction line of the project - the key route. It has significant effects in terms of shortening the construction period, improving ergonomics, and reducing costs. In this paper, the progress of comprehensive control of the second phase of a power plant was plotted using network technology. The original cross road plan to arrange earth excavation to the third unit to put into production, the total construction period is 824 days (ie 27 months), the use of network technology in the lap network plan, the main plant hoisting project and the boiler hoisting overlap construction, the total duration Only 752 days (ie 24.7 months).