丹江口水利枢纽在党的英明领导与总路线的光辉照耀下,通过十万劳动大军的努力,第一期基坑工程已胜利完成,第二期围堰截流工程并在1959年12月26日高速度的胜利合龙。目前已进入新的施工高潮。二期上游横向围堰的修筑及二期基坑开挖正大力开展,为实现工地党委提出的两年基本建成;一年扫尾的施工方案打下了可靠的基础。一期围堰工程已胜利完成其历史任务,二期围堰正在填筑,并开始发生作用。通过一、二期围堰工程的实践,使我们对一期围堰的布置、型式和一二期围堰的相互关系,有了一些体会,特写在下面,供读者们参考。
Danjiangkou Water Control Project under the wise leadership of the party and the brilliant shining of the general line, through the efforts of one hundred thousand labor force, the first phase of foundation pit project has been successfully completed, the second phase of cofferdam closure project and in December 26, 1959 high speed The victory of the dragon. Has now entered a new construction boom. The construction of the second-stage upstream transverse cofferdam and the excavation of the second-stage foundation pit are being vigorously carried out. The two-year basic completion plan put forward by the party committee of the construction site has been basically completed. The construction plan for finishing construction in the first year has laid a solid foundation. A cofferdam project has successfully completed its historical mission, two cofferdams are filling and began to play a role. Through the practice of one or two cofferdam projects, we have some experience on the arrangement and type of cofferdam and the correlation between the first and second cofferdams. The following is a brief introduction for readers’ reference.