美刊《钢铁工程师》六月刊载题为《日本钢管公司扇岛钢铁厂的建设与操作》一文,摘要如下: 扇岛厂是建在东京湾人造岛上的钢铁厂。建设分方二二期,一期工程已完成,二期预计在一九七九年六月完成,最终规模为年产粗钢六百万吨。除了填海造地外,总投资估计为三十五亿五千万美元,其中百分之二十用于环保;折合形成每吨产钢能力的投资为五百九十美元(按二百六十日元等于一美元计)。
A paper entitled “Construction and Operation of the Japanese Steel Pipe Company,” which is published by the Steel Engineer in the United States in June, is summarized as follows: The Fan Island Plant is a steel plant built on the artificial island of Tokyo Bay. The second and second phases of construction will be completed. The first phase of the project has been completed and the second phase is expected to be completed in June 1979 with an annual output of 6 million tonnes of crude steel. In addition to land reclamation, the total investment is estimated at 3.55 billion U.S. dollars, of which 20% is for environmental protection. The investment equivalent to producing steel capacity per tonne is US $ 59 (based on two hundred and sixty Yen equals one dollar.)