尼泊尔最大的水电站在工期推迟 2a后 ,将于2 0 0 2年 1月投入运行。投资 4 .5亿美元的卡利甘达基电站 (在Syangja西部地区 ) ,从 1997年开工以来 ,一直受到设计和技术问题的困扰。由这个 144MW的电站发出的电能 ,将为电力系统提供更大的运行灵活性 ,并减少国家对进口
The largest hydropower station in Nepal will be put into operation in January 2002 after a two-year delay in construction. The 450 million U.S. dollar Kaligandaki Power Station (in the western Syangja region) has been plagued by design and technical problems since its start in 1997. The power generated by this 144 MW plant will provide greater operational flexibility for the power system and reduce the country’s need for imports