北大医信的张海冬是在3月17日进入项目组的,当时需求分析的工作已经完成,明确了“冲7”任务并已把任务下发给研发团队(包括开发组、测试组和实施组)。从3月17日到5月9日,一共38个工作日,近8周时间。研发团队按照项目的整体规划,逐周进行工作的落实。第一周,研发团队共收到40件需求单,研发团队首先对40件需求单进行了需求确认。开发团队、测试团队、实施团队和业务组坐在一起,对每个需求进行逐项讨论,有问题的需求当场确定修改方案,确保研发团队各个环节正确理解需求,没有异议,之后制定开发计划。接收需求以后,研发团队并没有直接进行编码,而是开展了功能设计和接口设计。根据需求单,研发团队共编写了18篇功能设计和9篇接口设计。
Zhang Haidong from Peking University Medical College entered the project team on March 17, when the demand analysis was completed and the task of “Rushing 7” was clearly defined and assigned to the R & D team (including development team, testing team and Implementation group). From March 17 to May 9, a total of 38 working days, nearly 8 weeks time. R & D team in accordance with the overall project planning, weekly implementation of the work. In the first week, the R & D team received a total of 40 demand sheets. The R & D team first identified the needs of 40 demand sheets. Development team, test team, implementation team and business team sit together, discuss each requirement one by one, the problem needs to be identified on the spot to modify the program to ensure that all aspects of R & D team correctly understand the demand, no objection, and then develop a development plan. After receiving the requirements, R & D team did not directly encode, but to carry out the functional design and interface design. According to the demand list, the R & D team compiled a total of 18 functional designs and 9 interface designs.