一○一厂炼钢场旧型莫根式煤气炉,原系「薄煤层、厚渣层、高温操作」,煤气的质量低、数量少、特别自一九五三年第二季度平炉改大后,煤气供应不能满足平炉需要的情况十分突出,平炉冶炼时间拉长,是该场连续七个月完不成任务的主要因素之一。八月以后,根据苏联专家纳依道夫斯基同志关于「加厚煤层降低出口温度」的建议,逐步改为「低温操作」,煤气质量和数量有了显著的提高,提供了平
One hundred and eleven factory old-style steel mills Morgen gas stove, the original “thin seam, thick slag layer, high temperature operation”, the quality of gas is low, the number is small, especially since the flat furnace in the second quarter of 1953 to change, Gas supply can not meet the needs of the hearth is very prominent, open-smelting elongated, is the field for seven consecutive months, one of the main tasks can not finish the task. After August, according to the suggestion of Soviet expert Ney Daudovsky on “reducing outlet temperature in thickened coal seams,” it was gradually changed to “low-temperature operation” with a significant improvement in the quality and quantity of gas, providing a flat