省冶金第二建设公司1975年6至8月在株洲氮水灌区最大的西塘渡槽工程中,成功地采用液压滑动模板,多快好省地施工了24米高的渡槽支架。该支架共40排,高24米,宽2.9米,每个重65吨,不便于预制吊装,一般是采用现浇的施工方法,但用木模现浇方法,按工期要求,至少需占用木材600米~3。采用液压滑动模板施工,不需大量的脚手架,除少许横梁底模和操作台铺板外,几乎不用木材。每一组同时施工四个排架,最高每班滑升速度为5米,
The Second Metallurgical Construction Company From June to August 1975, in the largest Xitang aqueduct project in the nitrogenous water irrigation area of Zhuzhou, the hydraulic sliding template was successfully used to construct a 24-meter-high aqueduct bracket more quickly and economically. The stent a total of 40 rows, 24 meters high, 2.9 meters wide, weighing 65 tons each, inconvenient for prefabricated hoisting, cast-in-place construction methods are generally used, but with wooden mold pouring method, according to schedule requirements, at least take up wood 600 meters ~ 3. The use of hydraulic sliding template construction, without a large amount of scaffolding, in addition to a small cross-beam bottom mold and console decking, almost no wood. Each group at the same time the construction of four shelves, the maximum speed of each class is 5 meters,