为了上水库堆石坝体填筑的正常施工,根据设计提供的堆石填筑参数进行了7场38组不同施工参数的对比试验,最终获得了最佳的施工参数和施工工艺,根据碾压试验的成果,确保了主坝坝体大型填筑工程的顺利完成,因此本施工工艺和施工参数具有极高的推广实用价值。
For the normal construction of the reservoir rockfill dam body filling, according to the design of the rockfill filling parameters, comparative experiments of 38 groups of 38 different construction parameters were carried out, and finally the best construction parameters and construction technology were obtained. According to the rolling The results of the test to ensure the successful completion of large-scale filling works of the main dam dam, so the construction technology and construction parameters have a very high practical value.