为了加快红水河上岩滩水电站工程的建设,广西壮族自治区电力局对能否在1988年实现截流的关键项目,即坝址区左岸土石方开挖工程,实行单项招标。参加投标的有6个单位,经过开标评议,葛洲坝工程局开挖分局以3,495万元的最低标价、提前两个月的最短工期(较标书要求工期)、交付优质标准工程和最佳施工方案中标。此项工程从1985年2月28
In order to accelerate the construction of the Hongshuihe Shangyantan hydropower station project, the Guangxi Zhuang Autonomous Region Electric Power Bureau implemented a single bidding for the key project for interception in 1988, namely the excavation of the earthwork on the left bank of the dam site. 6 units participated in the bidding. After reviewing the bids, the Gezhouba Engineering Bureau excavated the sub-bureau with a minimum price of 34.95 million yuan, the minimum period of two months ahead of schedule (compared with the required duration of bids), the delivery of quality standard projects, and the best construction plan. . This project was completed on February 28, 1985