【摘 要】经济的不断增长带动了铁路运输事业的迅速繁荣,在公路工程中,大跨度、特大跨度的桥梁工程越来越多。而在这些大桥、特大桥基础施工项目中,钻孔灌注桩地基处理技术的应用非常广泛。在桥梁基础工程中,由于钻孔灌注桩多数为水下施工,其施工过程很难进行全面观察,隐蔽性较强,成桩后的检测工作也较为困难,因此确保每一个施工环节的质量都至关重要。
【关键词】钻孔灌注桩;泥浆; 质量控制
Bored construction quality control analysis
Qiu Xiang-shi
(Zhejiang, China Road and Bridge Engineering Co., Ltd Lishu Zhejiang 323000)
【Abstract】Growing economic prosperity led to the rapid rail transport undertakings in highway projects, large-span, large-span bridge engineering more and more. In the bridge, bridge foundation construction project Bored foundation treatment technology is widely used. Bridge Foundations, due mostly bored underwater construction, it is difficult to fully observe the construction process, hidden strong pile after testing work is also more difficult, thus ensuring the quality of every aspect of the construction are essential.
【Key words】Bored;Mud;Quality control
钻孔灌注桩的施工大部分采用泥浆护壁成孔和干作业成灌注两类工艺,施工前期工作任何一个环节准备不充分,都将直接影响到整个工程的质量和工期,直至给建设方造成重大的经济损失和严重的社会影响。因此在施工前应认真熟悉施工场地和邻近区域的危房等特殊建筑物设计图纸及有关施工、技术规范,核查地质和有关灌注桩技术规范方面的相关资料,对灌注桩在施工过程中可能会发生的一些问题进行分析后制订出施工组织方案、对进场材料控制和每根桩的施工进行质控记录,以便有效地对桩基础施工质量加以控制,确保工程顺利通过验收。
1. 钻孔灌注桩施工技术的分析
(1)施工准备。根据工程现场调查,设计图纸等资料,对施工场地的地形地貌、地上地下水位、地质情况等进行详细分析。对地下管线及交叉道路中心里程、交叉角度及管线埋深等资料进行认真核对。桩位无水时,对场地进行清理,将桩基位置整平并夯实,如果施工现场较陡,可采用枕木或方木来搭设操作平台。
(2)泥浆制备。根据要求制备泥浆,泥浆材料、比重、粘度、含砂率等各项指标都应该在设计要求下确定,同时还需要进行相应的试验以保证泥浆质量。
(3)设置护筒。钻孔灌注桩所使用到的钢护筒长度必须符合要求。钢护筒下沉通常采用振动锤振动下沉。为了避免护筒变形,护筒内可设置几道临时的支撑,在护筒下沉时,及时将支撑拆除; 护筒下放时需要根据控制点,采用全站仪进行放样,并在平台上设置好桩位的临时控制点; 护筒下放时应该随时检查其平面位置,如果发现存在偏差应该及时校正。
(4)钻孔。为了保证成孔的质量,钻进时可采取钻头配重减压或水头压力等保证措施。在钻机就位以后,将其固定牢靠,避免在钻进过程中发生偏移。钻机顶端起吊滑轮转盘中心与钻孔中心应该保持在同一直线上,并随时检查钻进过程中的垂直度; 在施工过程中,为保证钻孔质量,成孔过程中应该做好泥浆护壁施工。对泥浆进行随时的稠度检测。
(5)清孔。在钻头钻进到设计深度之后,提升钻头与孔底保持 10 cm ~ 20 cm,注入密度较低的优质泥浆,将孔内的残渣、高密度泥浆换出。同时保持孔内水头,避免坍塌。
(6)钢筋笼制作与安装。钢筋笼制作应该符合设计要求。制作钢筋笼时应该先将焊接处的铁锈、油污以及砂浆等清理干净。将钢筋端头矫正顺直; 保证钢筋笼吊环的长度符合设计要求; 钢筋笼下放时应该对钢筋笼的焊缝进行逐节检查,保证焊缝、焊口的质量; 钢筋笼下放时要保持平顺,避免碰撞到孔壁,引起孔壁坍塌; 如果钢筋笼下放时受阻,不可强行下放,应该及时查找原因,并采取正确措施处理。
(7)安装导管。通常情况下采用无缝钢管作为导管,每节导管的长度应该在 2 m ~ 5 m 左右。导管可采用螺旋连接套进行连接,吊装前应该进行试拼,并进行压力测试,如果存在漏水现象先处理好。现场拼接时,应保证密封圈无破损、接头密实、顺直。
(8)混凝土灌注。在混凝土灌注之前需要进行二次清孔作业 ,对孔底沉淀层的厚度、泥浆的质量进行检测,保证其符合要求; 可采用规定型号的混凝土拌合机制拌混凝土,为了延长混凝土初凝时间,提高混凝土的和易性,可适当掺入一些外加剂; 首批混凝土灌注时,导管下口与孔底的距离应该保持在 20 cm ~ 25 cm,导管埋入混凝土中的深度不得低于 1 m; 灌注混凝土时,应该对混凝土顶面高程进行随时的检测,同时控制好导管的埋深; 保证混凝土灌注的连续性,避免导管内形成空隙体; 在混凝土面与钢筋笼接近时,导管的埋深要保证,避免钢筋笼上浮; 在混凝土灌注到钢筋笼一定深度以后,可将导管适当提升,保证钢筋笼在导管下端的埋深;为了保证桩头混凝土的灌注质量,导管可在最后灌注段上下移动,并保持桩顶超灌0.5 m ~ 1 m 左右。 (9)成桩检测。在混凝土桩达到一定强度后,可对桩体进行无损检测,以确保成桩质量。
2. 钻孔灌注桩施工的质量控制措施
2.1 成孔质量控制措施。
(1)采取隔孔施工的方法: 由于钻孔灌注桩是先成孔,再进行孔内灌注成桩,周围土体的偏移对桩身会产生一定的压力。尤其在成桩的初期,由于混凝土强度较低,这种压力容易影响到成桩质量,因此,应该采取隔孔施工的方法,控制好施工桩的距离,避免出现坍孔等问题。
(2)保证成桩的垂直度: 桩孔垂直度是保证钻孔灌注桩施工的前提条件。为了保证桩孔的垂直度,确定桩机的稳固性,可适当扩大桩机的支承面积,并经常性的对钻架及钻杆进行垂直度校正,在钢筋笼下放之前,还需要对孔径、斜度等指标进行检测。
(3)避免出现塌孔、缩径等现象: 如果在提钻过程中碰撞到孔壁,可能会出现坍孔现象。因此,在提出钻具后,应对成孔深度进行检测,如果发现孔深变化,应该重新下钻并清孔;为了避免塌孔、缩径等现象,不仅要对钻具长度进行复核,还需保证钻杆的顺直,可根据地质情况随时调整钻进速度; 在施工时,应随时对钻头直径进行复核,如发现钻头磨损严重,应及时调换。
2.2 成桩质量控制。
(1)保证原材料的质量: 要对进场的原材料进行严格检查和验收,保证原材料的质量符合施工要求。如果发现实样与质量保证书不符,应该立即进行复查,严禁不合格材料应用于工程当中。
(2)保证混凝土的配合比: 钻孔灌注桩采用的是导管灌注方式,容易出现混凝土离析现象,因此必须确保混凝土的配合比,减少离析现象的出现; 混凝土的配合比应该结合水泥品种、砂、石料的规格以及含水率来确定。为了保证每根桩的配合比都能满足要求,需要在混凝土搅拌时对配合比进行复核,并严格计量与测试,同时进行认真记录。
(3)防止出现断桩、夹层、堵管等现象: 混凝土灌注时应该对混凝土的搅拌时间及坍落度进行严格控制。如果搅拌时间不足很容易影响到混凝土的强度及坍落度。导管埋入混凝土的深度应控制好,防止导管底端高出混凝土面; 施工过程中还需要控制好灌注的工艺,控制好导管上升的速度,保证拔管的幅度,保证灌注的连续性。
3. 结束语
总之,由于钻孔灌注桩施工属于隐蔽性工程,其施工每个环节的质量控制都非常关键。因此必须做好其质量的控制工作,增强施工技术人员的实践经验和工作责任心,注重对钻孔灌注桩的检测工作,从而确保工程整体质量的有效增强。
参考文献
[1] 陈德营. 浅谈泥浆护壁钻孔灌注桩的施工质量控制[J]. 中华民居(下旬刊),2014,01:407.
[2] 黄文明. 钻孔灌注桩工程施工质量的控制与缺陷处理[J]. 工程建设与设计,2014,02:135-138+141.
[3] 刘建伟. 桥梁深水基础钻孔灌注桩施工技术概要[J]. 科技与企业,2014,02:169.
【关键词】钻孔灌注桩;泥浆; 质量控制
Bored construction quality control analysis
Qiu Xiang-shi
(Zhejiang, China Road and Bridge Engineering Co., Ltd Lishu Zhejiang 323000)
【Abstract】Growing economic prosperity led to the rapid rail transport undertakings in highway projects, large-span, large-span bridge engineering more and more. In the bridge, bridge foundation construction project Bored foundation treatment technology is widely used. Bridge Foundations, due mostly bored underwater construction, it is difficult to fully observe the construction process, hidden strong pile after testing work is also more difficult, thus ensuring the quality of every aspect of the construction are essential.
【Key words】Bored;Mud;Quality control
钻孔灌注桩的施工大部分采用泥浆护壁成孔和干作业成灌注两类工艺,施工前期工作任何一个环节准备不充分,都将直接影响到整个工程的质量和工期,直至给建设方造成重大的经济损失和严重的社会影响。因此在施工前应认真熟悉施工场地和邻近区域的危房等特殊建筑物设计图纸及有关施工、技术规范,核查地质和有关灌注桩技术规范方面的相关资料,对灌注桩在施工过程中可能会发生的一些问题进行分析后制订出施工组织方案、对进场材料控制和每根桩的施工进行质控记录,以便有效地对桩基础施工质量加以控制,确保工程顺利通过验收。
1. 钻孔灌注桩施工技术的分析
(1)施工准备。根据工程现场调查,设计图纸等资料,对施工场地的地形地貌、地上地下水位、地质情况等进行详细分析。对地下管线及交叉道路中心里程、交叉角度及管线埋深等资料进行认真核对。桩位无水时,对场地进行清理,将桩基位置整平并夯实,如果施工现场较陡,可采用枕木或方木来搭设操作平台。
(2)泥浆制备。根据要求制备泥浆,泥浆材料、比重、粘度、含砂率等各项指标都应该在设计要求下确定,同时还需要进行相应的试验以保证泥浆质量。
(3)设置护筒。钻孔灌注桩所使用到的钢护筒长度必须符合要求。钢护筒下沉通常采用振动锤振动下沉。为了避免护筒变形,护筒内可设置几道临时的支撑,在护筒下沉时,及时将支撑拆除; 护筒下放时需要根据控制点,采用全站仪进行放样,并在平台上设置好桩位的临时控制点; 护筒下放时应该随时检查其平面位置,如果发现存在偏差应该及时校正。
(4)钻孔。为了保证成孔的质量,钻进时可采取钻头配重减压或水头压力等保证措施。在钻机就位以后,将其固定牢靠,避免在钻进过程中发生偏移。钻机顶端起吊滑轮转盘中心与钻孔中心应该保持在同一直线上,并随时检查钻进过程中的垂直度; 在施工过程中,为保证钻孔质量,成孔过程中应该做好泥浆护壁施工。对泥浆进行随时的稠度检测。
(5)清孔。在钻头钻进到设计深度之后,提升钻头与孔底保持 10 cm ~ 20 cm,注入密度较低的优质泥浆,将孔内的残渣、高密度泥浆换出。同时保持孔内水头,避免坍塌。
(6)钢筋笼制作与安装。钢筋笼制作应该符合设计要求。制作钢筋笼时应该先将焊接处的铁锈、油污以及砂浆等清理干净。将钢筋端头矫正顺直; 保证钢筋笼吊环的长度符合设计要求; 钢筋笼下放时应该对钢筋笼的焊缝进行逐节检查,保证焊缝、焊口的质量; 钢筋笼下放时要保持平顺,避免碰撞到孔壁,引起孔壁坍塌; 如果钢筋笼下放时受阻,不可强行下放,应该及时查找原因,并采取正确措施处理。
(7)安装导管。通常情况下采用无缝钢管作为导管,每节导管的长度应该在 2 m ~ 5 m 左右。导管可采用螺旋连接套进行连接,吊装前应该进行试拼,并进行压力测试,如果存在漏水现象先处理好。现场拼接时,应保证密封圈无破损、接头密实、顺直。
(8)混凝土灌注。在混凝土灌注之前需要进行二次清孔作业 ,对孔底沉淀层的厚度、泥浆的质量进行检测,保证其符合要求; 可采用规定型号的混凝土拌合机制拌混凝土,为了延长混凝土初凝时间,提高混凝土的和易性,可适当掺入一些外加剂; 首批混凝土灌注时,导管下口与孔底的距离应该保持在 20 cm ~ 25 cm,导管埋入混凝土中的深度不得低于 1 m; 灌注混凝土时,应该对混凝土顶面高程进行随时的检测,同时控制好导管的埋深; 保证混凝土灌注的连续性,避免导管内形成空隙体; 在混凝土面与钢筋笼接近时,导管的埋深要保证,避免钢筋笼上浮; 在混凝土灌注到钢筋笼一定深度以后,可将导管适当提升,保证钢筋笼在导管下端的埋深;为了保证桩头混凝土的灌注质量,导管可在最后灌注段上下移动,并保持桩顶超灌0.5 m ~ 1 m 左右。 (9)成桩检测。在混凝土桩达到一定强度后,可对桩体进行无损检测,以确保成桩质量。
2. 钻孔灌注桩施工的质量控制措施
2.1 成孔质量控制措施。
(1)采取隔孔施工的方法: 由于钻孔灌注桩是先成孔,再进行孔内灌注成桩,周围土体的偏移对桩身会产生一定的压力。尤其在成桩的初期,由于混凝土强度较低,这种压力容易影响到成桩质量,因此,应该采取隔孔施工的方法,控制好施工桩的距离,避免出现坍孔等问题。
(2)保证成桩的垂直度: 桩孔垂直度是保证钻孔灌注桩施工的前提条件。为了保证桩孔的垂直度,确定桩机的稳固性,可适当扩大桩机的支承面积,并经常性的对钻架及钻杆进行垂直度校正,在钢筋笼下放之前,还需要对孔径、斜度等指标进行检测。
(3)避免出现塌孔、缩径等现象: 如果在提钻过程中碰撞到孔壁,可能会出现坍孔现象。因此,在提出钻具后,应对成孔深度进行检测,如果发现孔深变化,应该重新下钻并清孔;为了避免塌孔、缩径等现象,不仅要对钻具长度进行复核,还需保证钻杆的顺直,可根据地质情况随时调整钻进速度; 在施工时,应随时对钻头直径进行复核,如发现钻头磨损严重,应及时调换。
2.2 成桩质量控制。
(1)保证原材料的质量: 要对进场的原材料进行严格检查和验收,保证原材料的质量符合施工要求。如果发现实样与质量保证书不符,应该立即进行复查,严禁不合格材料应用于工程当中。
(2)保证混凝土的配合比: 钻孔灌注桩采用的是导管灌注方式,容易出现混凝土离析现象,因此必须确保混凝土的配合比,减少离析现象的出现; 混凝土的配合比应该结合水泥品种、砂、石料的规格以及含水率来确定。为了保证每根桩的配合比都能满足要求,需要在混凝土搅拌时对配合比进行复核,并严格计量与测试,同时进行认真记录。
(3)防止出现断桩、夹层、堵管等现象: 混凝土灌注时应该对混凝土的搅拌时间及坍落度进行严格控制。如果搅拌时间不足很容易影响到混凝土的强度及坍落度。导管埋入混凝土的深度应控制好,防止导管底端高出混凝土面; 施工过程中还需要控制好灌注的工艺,控制好导管上升的速度,保证拔管的幅度,保证灌注的连续性。
3. 结束语
总之,由于钻孔灌注桩施工属于隐蔽性工程,其施工每个环节的质量控制都非常关键。因此必须做好其质量的控制工作,增强施工技术人员的实践经验和工作责任心,注重对钻孔灌注桩的检测工作,从而确保工程整体质量的有效增强。