论文部分内容阅读
一、概况滴道发电厂是鸡西矿务局煤矸石综合利用自备电厂,装机容量为5万瓩,安装两台上海锅炉厂试制的130吨/时沸腾炉,两台北京重型电机厂生产的2.5万瓩汽轮发电机组。锅炉采用低热值煤矸石作为燃料,目前正处在边试验、边改造、边生产阶段。我厂是1975年经煤炭部、一机部、电力部共同商定在鸡西矿务局试用煤矸石发电,于1979年6月和1981年3月两机炉分别建成。整个电厂工程由电站、水库、输水管路、输电线路和综合利用五个部分组成,到83年末总投资为8256.2万元。自1979年试运以来,截止到83年底,
I. Overview Drop Road power plant is Jixi Mining Bureau coal gangue comprehensive utilization of self-owned power plant, installed capacity of 5 million 瓩, the installation of two Shanghai boiler plant trial production of 130 tons / hour boiling furnace, two Beijing Heavy Factory 2.5 Wan 瓩 Turbine Generator Set. Boilers using low calorific value gangue as fuel, is currently in the side of the test, while the transformation, while the production stage. I plant in 1975 by the Ministry of Coal, a machine department, the Ministry of Electric Power jointly agreed to trial in Jixi Mining Bureau coal gangue power generation, in June 1979 and March 1981 two machine were completed. The entire power plant project from the power plants, reservoirs, water pipelines, transmission lines and the comprehensive utilization of five parts, to the end of 83 a total investment of 82.562 million yuan. Since the trial operation in 1979, by the end of 83,