山东省青岛市城市煤制气厂,第一期工程自1985年5月1日破土动工以来,经过一年零十个月的紧张施工,于1987年3月24日正式投产送气。 煤制气厂位于青岛市海口区李村河入海处,为填海地,全厂总土方工程量为562731立方米,占地面积为25.83公顷。第一期工程总投资约5600万元。规模为日产城市煤气14万立方米,水煤气7.68万立方米,居民用户为3.6万户,其余为公共福利和工业用户。
After the groundbreaking of the first phase of the Qingdao Coal-based Gas Plant in Shandong Province on May 1, 1985, it was officially put into operation on March 24, 1987 after ten years of intense construction. The coal gas plant is located in the Li Cun River, Haikou District, Qingdao City. It is a land reclamation site with a total earthwork volume of 562,731 cubic meters and an area of 25.83 hectares. The total investment for the first phase of the project is about 56 million yuan. The scale of Nissan City gas 140,000 cubic meters, water and gas 76,800 cubic meters, residential users for 36,000, the rest for the public welfare and industrial users.