大冶铁矿尖林山采区通风系统节能技术改造课题,是由武钢大冶铁矿、武钢矿山部、治金部安全环保研究院共同承担的,他们针对大冶铁矿尖林山采区原用的单一主扇中央抽出式通风系统不能满足生产需要,主扇和通风系统不匹配、能耗大、通风效果差等问题,深入进行调查研究,综合分析了国内同类型矿山的通风状况和节能风机的研制成果,确定部分变更原通风网路结构,施工新的回风井巷,合理调整上下盘风路,完善通风系统。同时在主要回风井巷采用最佳经济断面和三台风机并联取代单一主扇的装置方式,以及低压补偿电容器补偿电网功率因数等节能技术,较好地达到了预期目标。
Daye Iron Mine Shaolin mining area Ventilation system energy-saving technological transformation of the subject, by the Wugang Daye Iron Mine, Wugang Mining Department, the Ministry of Security Institute of Environmental Protection jointly shared their commitment to Daye Mine Iron Ore Mining original use The single main fan central withdrawable ventilation system can not meet the production needs, main fan and ventilation system does not match, energy consumption, poor ventilation and other issues, in-depth investigation and study, a comprehensive analysis of the domestic mine ventilation and energy-saving fan Of the development results, to determine part of the original change the ventilation network structure, the construction of a new return airway, a reasonable adjustment of the upper and lower plate airway, improve the ventilation system. In the meantime, the energy-saving technologies such as the optimal economic section and the parallel replacement of a single main fan by three turbines in the main return air shaft and the energy-saving technologies such as low-voltage compensation capacitor to compensate grid power factor have been satisfactorily achieved.