原电力工业部基本建设总局頒发的“烘爐煮爐規程”(試行本)是根据以往习慣制定的。該規程規定完成重型爐墙烘燥的时間需要10~14天。这样长的时間,显然与发电設备的快速安装、快速发电的要求是不相适应的。所以最近某些工程在苏联专家指导下,实际上已經不完全照該規程进行烘、煮爐了。电力建设科学技术研究所針对这个实际問題进行了研究。研究如何的升溫数值和升溫速度可以达到既能縮短烘燥时間,又能保証烘燥質量的要求。經过一系列的試驗后,証明重型炉墙的烘燥时間可以大大縮短。 (一)快速升溫試验研究的程序是先分別对耐火磚及紅磚的灰缝及磚本身进行快速升溫試驗,証明快速升温对上述試件沒有影响后,再在小型爐墙上进行快速升溫試驗,然后再在40吨/时鍋爐上实际試驗.
The “Oven Boiler Regulation” (Trial Version) issued by the Basic Construction Administration of the former Ministry of Electric Power Industry is based on past habits. This regulation stipulates that it takes 10 ~ 14 days to complete the drying time of heavy-duty wall. Such a long period of time is clearly incompatible with the rapid installation of power generation equipment and the requirement of fast power generation. Therefore, under the guidance of Soviet experts recently, some projects have actually not completely baked and boiled according to the procedures. Electric Power Research Institute of Science and Technology to address this practical issues were studied. Study how the heating value and heating rate can be achieved both to shorten the drying time, but also to ensure the quality requirements of the drying. After a series of tests, it proved that the drying time of heavy-duty furnace wall can be greatly shortened. (A) rapid heating test research program is to respectively refractory brick and red brick gray seam and the brick itself rapid heating test to prove that the rapid heating has no effect on the specimen, and then in a small furnace wall rapid heating test , And then the actual test on a 40 t / h boiler.