摘要:随着现代桥梁施工技术的发展,人们对于施工技术的要求越来越高。部分桥梁在设计、施工过程中,由于通车、通航、场地等因素的限制,不能或不宜搭设满堂支架,就需要用到悬臂挂篮法施工技术,本文介绍了悬臂挂篮法及其施工中的一些要点,为此类施工提供参考。
关键词:桥梁 悬臂挂篮 施工要点
Abstract: with the development of modern bridge construction technology, the construction technology requirements more and more high. Some Bridges in the design, construction process, due to traffic, navigation, sites and other factors limit, cannot or should not be built full framing, it needs to use the cantilever hanging basket method, this paper introduces the construction technology of cantilever hanging basket method and construction of some key points for the construction to provide the reference.
Keywords: bridge cantilever construction points hanging basket
中图分类号:U445 文献标识码:A 文章编号:2095-2104(2013)
一、桥梁施工悬臂挂篮法
挂篮是一个能沿梁顶滑动或滚动的承重构架,其锚固悬挂在已施工梁段上,在挂篮上可进行下一梁段的模板、钢筋、预应力管道的安设,混凝土灌注和预应力张拉,灌浆等作业。完成一个阶段的循环后,挂篮即可前移并固定,进行下一阶段的悬灌,如此循环直至悬臂灌注完成。用挂篮悬臂施工的主要工作内容包括:在墩顶浇筑起步梁段(0#块),在起步梁段上拼装悬灌挂篮并依次分段悬浇梁段;边跨及中跨合拢。
(一)挂篮分类
挂篮按构造形式可分为桁架式(包括平弦无平衡重式、菱形、弓弦式)、斜拉式、型钢式及混合式四种;
挂篮按抗倾覆平衡式可分为压重式、锚固式和半压重锚固式三种;
按挂篮走行方法可分为一次走行到位和两次走行到位两种;
按其移动方式可分为滚动式、滑动式和组合式三种
(二)挂篮悬臂灌注施工的主要工艺程序
灌注0号段及墩梁临时锚固;拼装挂篮;灌注1号段; 张拉预应力钢索;挂篮前移、调整、锚固;灌注下一梁段(挂篮前移,按立模标高设顶底模标高;浇筑混凝土,养护;张拉预应力钢索。)依次类推完成悬臂灌注;挂篮拆除;边跨合拢;中跨合拢。
(三)悬臂挂篮法施工特点
悬臂施工适应于梁的上翼缘承受拉应力的桥梁形式。悬臂浇筑法是用挂篮就地分段现浇,待每段混凝土养护并张拉后,再将挂篮前移,以浇筑下一节段之用。使用挂篮就地浇筑的方法,可在不设支架和不使用大型吊机的情况下,浇筑较大跨径的悬臂梁桥、连续梁桥以及刚构桥等类型的上部构造。悬臂浇注的每一段将要承受随后浇注段的结构自重及施工机具人员等载荷,并要保持悬臂对称和平衡及安全稳定。一般悬臂浇注的一个节段长3~8米,不宜超过8米。节段太长,将会增加结构与挂篮的静载,也会引起前面节段太大的施工内力。
二、悬臂挂篮法施工要点
(一)0 号块的施工
在各梁段中0#段中纵向预应力筋根数最多因此预应力筋管道也最多同时普通钢筋密集构造复杂施工难度极大是整个梁体施工的关键对下一阶段施工至关重要。墩顶0号块的施工一般均在墩顶托架上立模现浇并且需要在施工过程中设置临时梁墩锚固或支撑措施使0号块能承受两侧施工时产生的不平衡弯矩
(二)挂篮制造与拼装
挂篮的基本构件如主纵梁、上下横梁、下纵梁、斜拉杆以及吊带等在工厂分件制作,完成后在工厂进行试拼,通过验收合格后作出标记,分散件运至施工现场。在运输过程中,应采取有效措施,防止吊装和运输变形。挂篮组装在0#块上进行:先将混凝土主梁对应于挂篮滑道的位置找平,铺设垫梁,将挂篮滑道精确定位,并用φ32精轧螺纹钢筋将滑道固定在主梁上;吊装挂篮主纵梁,并加上后锚;安装立柱、横联和斜拉杆,形成三角桁架;吊装上横梁,安装前后吊杆;吊装下横梁,并与吊杆相连;吊装下纵梁,形成底模平台;吊装挂篮侧模,完成挂篮组装(内模待绑好底板钢筋后再吊入,以后各段施工时,可直接由已浇梁段内抽出)。挂篮构件由吊车吊装。 挂蓝拆除按相反顺序进行。 挂蓝组装完成后,进行试压,以消除其非弹性变形,检验挂篮的安全性能,并测试其弹性性能,以便为施工控制计算提供准确数据。 经检验符合强度、刚度、安全性等要求并经监理工程师批准后,即可投使用。
临时固结
对于连续箱梁,梁与墩未固结在一起,施工时,两侧悬浇施工难以保持绝对平衡,必须在施工中采取临时固结措施,使梁具有抗弯能力。临时固结一般采用在支座两侧临时加预应力筋,梁和墩顶之间浇注临时混凝土垫块。将梁固结在桥墩上,使梁具有一定的抗弯能力。在条件成熟时,再采用静态破碎方法,解除固结。
临时固结是连续梁需采用悬浇施工工艺施工作业时,且连续梁与桥墩间具有(设计)桥梁支座支撑而采用的一种固结方式,并不是所有的预应力悬浇连续梁都需要作临时固结。常用的固结方式有以下几种:
1、在承台和0#块之间设置临时支墩,见图(a)。临时支墩一般采用钢管混凝土或钢筋混凝土立柱。采用穿过临时支墩的预应力筋进行承台与0#块梁底之间的固结,预应力筋下端通过预埋钢筋板等锚固在承台内,上端在箱梁底(顶)板张拉并锚固使整个支墩在施工过程中始终受压。
2、在桥墩墩顶和主梁0#块之间设置临时支座和预应力筋,见图(b),通过临时支座和预应力筋来承受悬臂施工中产生的不平衡弯矩。这种设置方法构造简单,制作、拆装方便、安全可靠。
3、在桥墩旁设置临时托架(依托墩上的预埋件),见图(c),支撑主梁0#块,用以平衡主梁悬浇期间的不平衡荷载。当墩身较高时,优势较为明显。
4、在桥墩旁设置临时支承(不依托墩身、承台),见图(d),支撑主梁0#块,用以平衡主梁悬浇期间的不平衡荷载。当承台面积较小且墩身較低时,可以选用。
(四)梁段混凝土的浇筑
梁段混凝土的悬臂浇筑一般用泵送,塌落度一般控制在14-18cm,并应随温度变化及运输和浇注速度作适当调整。
其注意事项如下:
1、箱梁各阶段混凝土在灌注前,必须严格检查挂篮中线,挂篮底模标高;纵、横、竖三向预应力束管道;钢筋、锚头、人行道及其它预埋件的位置,认真核对无误后方可灌注混凝土。箱梁各阶段立模标高=设计标高+预拱度+挂篮满载后自身变形。后灌注的梁段应在已施工梁段有关实测结果的基础上作适当调整,已逐渐消除误差,保证结构线性匀顺。
2、若能全断面一次灌注最好,否则应按以下顺序灌注。(1)二次灌注:第一次由底板至腹板下承托;第二次为剩余部分。(2)三次灌注:第一次由底板至腹板下承托;第二次是腹板下承托至腹板上承托预应力管道密集处以上,第三次由腹板上承托至顶板。
3、混凝土的灌注宜先从挂篮前端开始,以使挂篮的微小变形大部分实现,从而避免新、旧混凝土间产生裂缝。
4、各阶段预应力束管道在灌混凝土前,宜在波纹管内插入硬塑管作衬填,以防管道被压扁;管道的定位钢筋应用短钢筋做成井字形,并与箱梁钢筋网固定,定位钢筋网架间距應保持在0.2-0.8m左右,以防混凝土振捣过程中波纹管道上浮,引起预应力张拉时产生沿管道法向的分力,轻则产生梁体的内力分布不合理,重则产生混凝土崩裂,酿成严重事故。
5、施工时应在挂篮上设风雨蓬,避免混凝土因日晒雨淋而严重影响质量。冬季施工应备保温设施。有条件时,挂篮可以配备能保证全天候作业的设备,以提高作业效率和保证质量。
6、箱梁混凝土灌注完毕后,立即用通孔器检查管道,处理因万一漏浆等情况出现的堵管现象。
(五)预应力混凝土连续梁悬灌施工的合拢
1、掌握合拢期间的气温预报情况,测试分析气温变化规律,以确定合拢时间并为选择合拢锁定方式提供依据。
2、根据结构情况及梁温的可能变化情况,选定适宜的合拢方式并作力学建算。
3、选择日气温较低、温度变化幅度较小时锁定合拢口并灌注合拢段混凝土。
4、合拢口的锁定,应迅速、对称地进行,先将外刚性支撑一段与梁端预埋件焊接(或栓接),而后迅速将外刚性支撑另一端与梁连接,临时预应力束也应随之快速张拉。在合拢口锁定后,立即释放一侧的固结约束,使梁一端在合拢口锁定的连接下能沿支座左右伸缩。
5、合拢口混凝土宜比梁体提高一级,并要求早强,最好采用微膨胀混凝土,并须作特殊配比设计,浇注时应认真振捣和养护。
6、为保证浇筑混凝土过程中,合拢口始终处于稳定状态,必要时浇注之前可在各悬臂端加与混凝土重量相等的配重,加、卸载均因对称梁轴线进行。
7、混凝土达到设计要求的强度后,先部分张拉预应力钢索,然后解除劲性骨架,最后按设计要求张拉全桥剩余预应力束,当利用永久束时,只需按设计顺序将其补拉至设计张拉力即可。
8、临时束的张拉力一般宜在0.45-0.5Rjy,以防在合拢过程中预应力束过载报废而需要重新更换新束。
结束语
悬臂浇筑法施工是目前大跨径桥梁施工中采用较普遍的方法之一,它具有施工简便、结构整体性好等诸多优点。在悬臂挂篮施工中一定要把握好施工要点,控制施工质量,使它更广泛的应用于桥梁施工。
参考文献
[1] 杨文渊.桥梁施工工程师手册[K].人民交通出版社,2007.
[2] 中交第一公路工程局.公路桥涵施工技术规范[S].人民交通出版社,2000.
[3] 魏红一.桥梁施工及组织管理[M].人民交通出版社,2008.
[4] 雷俊卿.预应力混凝土连续梁桥[M].北京:人民交通出版社,2009.
[5] 李建中.预应力混凝土连续梁桥和刚架桥的时效分析[J].石家庄铁道学院学报,2011,13(4).
关键词:桥梁 悬臂挂篮 施工要点
Abstract: with the development of modern bridge construction technology, the construction technology requirements more and more high. Some Bridges in the design, construction process, due to traffic, navigation, sites and other factors limit, cannot or should not be built full framing, it needs to use the cantilever hanging basket method, this paper introduces the construction technology of cantilever hanging basket method and construction of some key points for the construction to provide the reference.
Keywords: bridge cantilever construction points hanging basket
中图分类号:U445 文献标识码:A 文章编号:2095-2104(2013)
一、桥梁施工悬臂挂篮法
挂篮是一个能沿梁顶滑动或滚动的承重构架,其锚固悬挂在已施工梁段上,在挂篮上可进行下一梁段的模板、钢筋、预应力管道的安设,混凝土灌注和预应力张拉,灌浆等作业。完成一个阶段的循环后,挂篮即可前移并固定,进行下一阶段的悬灌,如此循环直至悬臂灌注完成。用挂篮悬臂施工的主要工作内容包括:在墩顶浇筑起步梁段(0#块),在起步梁段上拼装悬灌挂篮并依次分段悬浇梁段;边跨及中跨合拢。
(一)挂篮分类
挂篮按构造形式可分为桁架式(包括平弦无平衡重式、菱形、弓弦式)、斜拉式、型钢式及混合式四种;
挂篮按抗倾覆平衡式可分为压重式、锚固式和半压重锚固式三种;
按挂篮走行方法可分为一次走行到位和两次走行到位两种;
按其移动方式可分为滚动式、滑动式和组合式三种
(二)挂篮悬臂灌注施工的主要工艺程序
灌注0号段及墩梁临时锚固;拼装挂篮;灌注1号段; 张拉预应力钢索;挂篮前移、调整、锚固;灌注下一梁段(挂篮前移,按立模标高设顶底模标高;浇筑混凝土,养护;张拉预应力钢索。)依次类推完成悬臂灌注;挂篮拆除;边跨合拢;中跨合拢。
(三)悬臂挂篮法施工特点
悬臂施工适应于梁的上翼缘承受拉应力的桥梁形式。悬臂浇筑法是用挂篮就地分段现浇,待每段混凝土养护并张拉后,再将挂篮前移,以浇筑下一节段之用。使用挂篮就地浇筑的方法,可在不设支架和不使用大型吊机的情况下,浇筑较大跨径的悬臂梁桥、连续梁桥以及刚构桥等类型的上部构造。悬臂浇注的每一段将要承受随后浇注段的结构自重及施工机具人员等载荷,并要保持悬臂对称和平衡及安全稳定。一般悬臂浇注的一个节段长3~8米,不宜超过8米。节段太长,将会增加结构与挂篮的静载,也会引起前面节段太大的施工内力。
二、悬臂挂篮法施工要点
(一)0 号块的施工
在各梁段中0#段中纵向预应力筋根数最多因此预应力筋管道也最多同时普通钢筋密集构造复杂施工难度极大是整个梁体施工的关键对下一阶段施工至关重要。墩顶0号块的施工一般均在墩顶托架上立模现浇并且需要在施工过程中设置临时梁墩锚固或支撑措施使0号块能承受两侧施工时产生的不平衡弯矩
(二)挂篮制造与拼装
挂篮的基本构件如主纵梁、上下横梁、下纵梁、斜拉杆以及吊带等在工厂分件制作,完成后在工厂进行试拼,通过验收合格后作出标记,分散件运至施工现场。在运输过程中,应采取有效措施,防止吊装和运输变形。挂篮组装在0#块上进行:先将混凝土主梁对应于挂篮滑道的位置找平,铺设垫梁,将挂篮滑道精确定位,并用φ32精轧螺纹钢筋将滑道固定在主梁上;吊装挂篮主纵梁,并加上后锚;安装立柱、横联和斜拉杆,形成三角桁架;吊装上横梁,安装前后吊杆;吊装下横梁,并与吊杆相连;吊装下纵梁,形成底模平台;吊装挂篮侧模,完成挂篮组装(内模待绑好底板钢筋后再吊入,以后各段施工时,可直接由已浇梁段内抽出)。挂篮构件由吊车吊装。 挂蓝拆除按相反顺序进行。 挂蓝组装完成后,进行试压,以消除其非弹性变形,检验挂篮的安全性能,并测试其弹性性能,以便为施工控制计算提供准确数据。 经检验符合强度、刚度、安全性等要求并经监理工程师批准后,即可投使用。
临时固结
对于连续箱梁,梁与墩未固结在一起,施工时,两侧悬浇施工难以保持绝对平衡,必须在施工中采取临时固结措施,使梁具有抗弯能力。临时固结一般采用在支座两侧临时加预应力筋,梁和墩顶之间浇注临时混凝土垫块。将梁固结在桥墩上,使梁具有一定的抗弯能力。在条件成熟时,再采用静态破碎方法,解除固结。
临时固结是连续梁需采用悬浇施工工艺施工作业时,且连续梁与桥墩间具有(设计)桥梁支座支撑而采用的一种固结方式,并不是所有的预应力悬浇连续梁都需要作临时固结。常用的固结方式有以下几种:
1、在承台和0#块之间设置临时支墩,见图(a)。临时支墩一般采用钢管混凝土或钢筋混凝土立柱。采用穿过临时支墩的预应力筋进行承台与0#块梁底之间的固结,预应力筋下端通过预埋钢筋板等锚固在承台内,上端在箱梁底(顶)板张拉并锚固使整个支墩在施工过程中始终受压。
2、在桥墩墩顶和主梁0#块之间设置临时支座和预应力筋,见图(b),通过临时支座和预应力筋来承受悬臂施工中产生的不平衡弯矩。这种设置方法构造简单,制作、拆装方便、安全可靠。
3、在桥墩旁设置临时托架(依托墩上的预埋件),见图(c),支撑主梁0#块,用以平衡主梁悬浇期间的不平衡荷载。当墩身较高时,优势较为明显。
4、在桥墩旁设置临时支承(不依托墩身、承台),见图(d),支撑主梁0#块,用以平衡主梁悬浇期间的不平衡荷载。当承台面积较小且墩身較低时,可以选用。
(四)梁段混凝土的浇筑
梁段混凝土的悬臂浇筑一般用泵送,塌落度一般控制在14-18cm,并应随温度变化及运输和浇注速度作适当调整。
其注意事项如下:
1、箱梁各阶段混凝土在灌注前,必须严格检查挂篮中线,挂篮底模标高;纵、横、竖三向预应力束管道;钢筋、锚头、人行道及其它预埋件的位置,认真核对无误后方可灌注混凝土。箱梁各阶段立模标高=设计标高+预拱度+挂篮满载后自身变形。后灌注的梁段应在已施工梁段有关实测结果的基础上作适当调整,已逐渐消除误差,保证结构线性匀顺。
2、若能全断面一次灌注最好,否则应按以下顺序灌注。(1)二次灌注:第一次由底板至腹板下承托;第二次为剩余部分。(2)三次灌注:第一次由底板至腹板下承托;第二次是腹板下承托至腹板上承托预应力管道密集处以上,第三次由腹板上承托至顶板。
3、混凝土的灌注宜先从挂篮前端开始,以使挂篮的微小变形大部分实现,从而避免新、旧混凝土间产生裂缝。
4、各阶段预应力束管道在灌混凝土前,宜在波纹管内插入硬塑管作衬填,以防管道被压扁;管道的定位钢筋应用短钢筋做成井字形,并与箱梁钢筋网固定,定位钢筋网架间距應保持在0.2-0.8m左右,以防混凝土振捣过程中波纹管道上浮,引起预应力张拉时产生沿管道法向的分力,轻则产生梁体的内力分布不合理,重则产生混凝土崩裂,酿成严重事故。
5、施工时应在挂篮上设风雨蓬,避免混凝土因日晒雨淋而严重影响质量。冬季施工应备保温设施。有条件时,挂篮可以配备能保证全天候作业的设备,以提高作业效率和保证质量。
6、箱梁混凝土灌注完毕后,立即用通孔器检查管道,处理因万一漏浆等情况出现的堵管现象。
(五)预应力混凝土连续梁悬灌施工的合拢
1、掌握合拢期间的气温预报情况,测试分析气温变化规律,以确定合拢时间并为选择合拢锁定方式提供依据。
2、根据结构情况及梁温的可能变化情况,选定适宜的合拢方式并作力学建算。
3、选择日气温较低、温度变化幅度较小时锁定合拢口并灌注合拢段混凝土。
4、合拢口的锁定,应迅速、对称地进行,先将外刚性支撑一段与梁端预埋件焊接(或栓接),而后迅速将外刚性支撑另一端与梁连接,临时预应力束也应随之快速张拉。在合拢口锁定后,立即释放一侧的固结约束,使梁一端在合拢口锁定的连接下能沿支座左右伸缩。
5、合拢口混凝土宜比梁体提高一级,并要求早强,最好采用微膨胀混凝土,并须作特殊配比设计,浇注时应认真振捣和养护。
6、为保证浇筑混凝土过程中,合拢口始终处于稳定状态,必要时浇注之前可在各悬臂端加与混凝土重量相等的配重,加、卸载均因对称梁轴线进行。
7、混凝土达到设计要求的强度后,先部分张拉预应力钢索,然后解除劲性骨架,最后按设计要求张拉全桥剩余预应力束,当利用永久束时,只需按设计顺序将其补拉至设计张拉力即可。
8、临时束的张拉力一般宜在0.45-0.5Rjy,以防在合拢过程中预应力束过载报废而需要重新更换新束。
结束语
悬臂浇筑法施工是目前大跨径桥梁施工中采用较普遍的方法之一,它具有施工简便、结构整体性好等诸多优点。在悬臂挂篮施工中一定要把握好施工要点,控制施工质量,使它更广泛的应用于桥梁施工。
参考文献
[1] 杨文渊.桥梁施工工程师手册[K].人民交通出版社,2007.
[2] 中交第一公路工程局.公路桥涵施工技术规范[S].人民交通出版社,2000.
[3] 魏红一.桥梁施工及组织管理[M].人民交通出版社,2008.
[4] 雷俊卿.预应力混凝土连续梁桥[M].北京:人民交通出版社,2009.
[5] 李建中.预应力混凝土连续梁桥和刚架桥的时效分析[J].石家庄铁道学院学报,2011,13(4).