大渡河黄金坪水电站左岸厂房拟安装四台单机容量200MW的水轮发电机组,首台(4号)机组蜗壳于2014年1月4日开始安装,2014年3月25日完成,为2014年10月底发电机层工作面移交创造了有利条件,为确保2015年6月底首台机组按期发电奠定了坚实的基础。黄金坪电站左岸厂房蜗壳为金属蜗壳,分32节,重量210t,蜗壳钢板材料为ADB-610D,最大厚度40mm,最小厚度
The left bank plant of Huangjinping Hydropower Station in Dadu River intends to install four hydro generator sets with a single capacity of 200MW. The first (No. 4) unit volute was installed on January 4, 2014 and completed on March 25, 2014 for 2014 The transfer of the working face of the generator layer at the end of October has created favorable conditions and laid a solid foundation for ensuring the first unit will be scheduled to generate electricity by the end of June 2015. The volute of the left bank plant of Huangjinping Power Plant is a metal volute, which is divided into 32 sections and weighs 210t. The material of the volute is ADB-610D, the maximum thickness is 40mm and the minimum thickness