杭州市1986年底建成了第一座错层式多层车库,在4700平方米的土地上能停放320辆车,节约了城市用地,交付使用后,效果良好。 该工程位于杭州保俶路中段(图1),由浙江省机关事务管理局投资兴建,总建筑面积10040平方米。第一期工程设有三个出入口。待第二期工程上马后;将在该车库的第三层,标高6.2米处(现已留有联接口),增设一条双车道出入
Hangzhou built the first split-level multi-storey garage at the end of 1986, and it can park 320 vehicles on a land of 4,700 square meters, saving urban land and delivering good results after delivery. The project is located in the middle section of Baoji Road in Hangzhou (Figure 1). It is invested and built by the Zhejiang Provincial Authority, with a total construction area of 1,040 square meters. The first phase has three entrances. After the second phase of the project is launched, it will be on the third floor of the garage, 6.2 meters above sea level (there is now a joint interface), and a two-lane access will be added.