江西省武宁县盘溪水利枢纽是一座以发电为主的中型水利水电工程。实行建设监理制两年多来,在质量控制方面,从3个环节着手,即“事先控制,坚持开工许可证制;中间跟踪,坚持现场检查制;事后验收,坚持工程质量签证制’,对施工全过程实施监理。在进度控制方面,从纵向(年、月进度)和横向(单项工程进度)两个方向进行监控。在投资控制方面,监理站主要通过质量认证和工程项目、工程量审核进行监控。监理站从工程实际出发,针对地方中小型工程的特点及施工中存在问题和矛盾,逐步调整。明确各方的责权界限及互相关系,不断总结经验,探索和充实适合中小工程的行之有效..的监理内涵。
Panxi Water Control Project in Wuning County, Jiangxi Province is a medium-sized water conservancy and hydropower project based on power generation. Implementation of the system of supervision over more than two years, in terms of quality control, from three aspects, namely, “control in advance, adhere to the permit system; intermediate tracking, insisting on-site inspection system; post-acceptance, adhere to the project quality visa system,” The whole process of construction supervision .In progress control, from the vertical (annual, monthly progress) and horizontal (single project progress) in both directions for monitoring.In the investment control, supervision station mainly through quality certification and engineering projects, engineering review Monitoring station.Monitoring station starting from the actual project, in view of the characteristics of small and medium-sized local projects and construction problems and contradictions, and gradually adjust the parties clear the boundaries of liability and mutual relations, and constantly sum up experience to explore and enrich the appropriate small and medium projects Effective supervision of the connotation.