隧洞施工过程是一个由钻孔、爆破、出碴、喷锚衬砌等工序组成的循环施工过程.在这个过程中,由于每道工序的完成时间可能是随机的,每个工作循环都可能产生随机排队现象.这样很可能在某一个循环作业中出现“拥塞口”现象而影响其它的循环作业.对于这类施工过程,如采用一般网络模型(CPM/PERT)来表达,极为复杂,节点或矢线数甚至可能要以成千上万计:且难以反映施工过程中的随机时间因素及其影响.本文提出采用循环仿真随机网络来分析隧洞施工过程.通过计算机对隧洞施工的循环过程和随机时间的模拟,可以得到不同资源水平和施工组织情况下的工期、成本;并通过灵敏度分析可以寻求合理的机械设备配套组合、理想的工期及成本方案.
The tunnel construction process is a cyclic construction process consisting of drilling, blasting, ballasting, shotcrete lining, etc. In this process, because the completion time of each process may be random, each working cycle may produce random It is very likely that there will be a phenomenon of “congestion in the mouth” during a certain cycle operation, which will affect other cycle work. For such construction process, such as using the general network model (CPM / PERT) to express, it is extremely complicated that the node or vector The number of lines may even need to be tens of thousands: it is hard to reflect the random time factor and its influence during the construction process.This paper proposes to use the random network of cyclic simulation to analyze the tunnel construction process, and through the computer to the tunnel construction cycle and random time The simulation can get the construction period and cost under different resource levels and construction organizations; and through the sensitivity analysis, we can seek a reasonable combination of mechanical equipment, the ideal schedule and cost options.