7月28日,马钢热烧结改建球团工程顺利竣工投产,开创了马钢建设史上利用部分存量资产边生产、边施工的新纪录。 热烧结改建球团工程,是马钢今年继一钢平炉改转炉之后,保护环境、淘汰落后的又一重点工程。马钢一烧结厂1958年建成,有5台小烧结机,总面积为132.5m~2。改造后的马钢一烧结厂将拥有新建8m~2竖炉2座,80m~2带冷机1台,50m~2电除尘器2台,直径6m的圆盘造球机4台,同时工程还对原配料系统以及公用辅助设施进行相应的改造。工程于2001年2月5日破土动工,到7月15日热负荷试车,仅用了161天。 该工程由马钢自己筹资设计、承建.其设备装备全部国产化,其中大部分机械设备由马钢制
July 28, Maanshan Thermal Sintering Pelletizing Project successfully completed and put into production, creating a history of Maanshan Iron and Steel in the history of the use of some of the existing stock of assets while production and construction of a new record. Thermal sintering reconstruction pelletizing project is Ma Steel this year, following a flat open hearth converter, the protection of the environment, eliminate backwardness and another key project. Magang a sintering plant built in 1958, there are 5 small sintering machine, a total area of 132.5m ~ 2. The transformed Maanshanyi Sintering Factory will have 2 new 8m ~ 2 shaft furnaces, 1 cold-bed machine with 80m ~ 2, 2 electrostatic precipitators of 50m ~ 2 and 4 disks of 6m in diameter. At the same time, Also the original ingredients system and public auxiliary facilities for the corresponding transformation. Engineering broke ground in February 5, 2001, to July 15 heat load test drive, only took 161 days. The project is designed and constructed by Masteel itself, with full localization of its equipment and equipment, most of which are made by Masteel