1958年12月21日深夜,下车室与台板組合体就位,到12月30日午间起动,并带5,000瓩負荷,机組起动試运过程中,真空系統严密性試驗、各式水泵和主体設备都是一次起动成功。第四瓦座振动为0.025公厘,而主体其他各部軸承振动均在0.01公厘左右,保证了工程質量。工程中,未出大小設备及人身伤亡事故,全年为国家节省了二万余元投資,全面地完成了国家跃进計划。获得这个成就的主要原因是。一、人人政治掛帅,树立了敢想敢干的共产主义风格在党的正确領导下,汽机段在三号机投入生产与贯彻省委扩大会議精神之后,进行了一次整风补課,
In the middle of the night of December 21, 1958, the combination of the alighting room and the platen was in place, and it started at midday on December 30th with a load of 5,000 Torr. During the trial run of the unit, the tightness test of the vacuum system and various types of pumps were performed. Both the main equipment and the main equipment are successfully started. The fourth susceptor vibration is 0.025 mm, while the vibration of the other parts of the main body is about 0.01 mm, which ensures the quality of the project. In the project, there were no accidents involving large-scale equipment and personal injuries. In the whole year, the country saved more than 20,000 yuan in investment and completed the national leap forward plan. The main reason for this achievement is. 1. Everyone is in charge of politics and establish a style of communism that dares to dare to do. Under the correct leadership of the party, after the Steam Turbine segment put into operation and implement the spirit of the provincial party committee to expand the meeting on the 3rd machine, a rectification course was carried out.