投资300万元的隧道密生产线,于5月20日正式投产,据近一个月的试用,炉温波动幅度小,产品质量稳定并有上升趋势,产量超原设计水平。预计年终可产2500t还还原铁粉,加之原生产能力,全年总产量预计将超过5000t。这不仅将满足原固定用户的需要,还将缓解一些计划外用户购粉难的需要。 产量上去了,质量怎么办?根据厂委要求,技术科、设备科积极主动、昼夜奋战,仅用5天时间,将原购南京
Investment of 3000000 yuan of tunnel dense production line, formally put into operation on May 20, according to nearly a month of trial, furnace temperature fluctuation is small, product quality is stable and there is an upward trend, the output of the original design level. The end of the year is expected to produce 2,500 tons of iron powder, plus the original production capacity, annual output is expected to exceed 5000t. This will not only meet the needs of the original fixed users, but also ease the need of some unscrambled users. Yield up, the quality of how to do? According to the requirements of the factory, technology, equipment, proactive, day and night fighting, only 5 days, the original purchase of Nanjing