论文部分内容阅读
新安江水电站建成于上世纪五十年代,是中国第一座自行设计、自制设备、自主建立的大型水力发电站,被称为中国水利电力史上的一座丰碑。电站最大坝高105米,总装机容量85.5千瓦,年发电量18.6亿千瓦小时,发挥着发电、调峰、防洪、灌溉、航运、养殖、旅游、水上运动等综合效益。在这一项目的实施过程中,淳安、遂安两座县城及1377个村庄被淹,计29万人移民,作为新中国成立后第一次最大规模的水库移民迁徙行动,记
Built in the 1950s, Xin’anjiang Hydropower Station is China’s first self-designed, self-made hydropower station built independently. It is regarded as a monument in the history of hydropower in China. The maximum dam height of 105 meters, the total installed capacity of 85.5 kilowatts, the annual generating capacity of 1.86 billion kilowatts hours, play a power generation, peak regulation, flood control, irrigation, shipping, aquaculture, tourism, water sports and other comprehensive benefits. During the implementation of this project, the two county towns of Chun’an and Sui’an and 1,377 villages were flooded, with a total population of 290,000. As the first large-scale reservoir resettlement move since the founding of new China,