筒体倒模施工的改进在某水泥厂筒仓施工中,我们采用了改进的倒模施工法,取得了较好的技术经济效果。其方法主要是取消了常规倒模的3套附着式三角挂架和内外吊篮,采用普通48脚手钢管和用卡扣连接组装的外侧活动升降吊挂脚手架,只需组装一次,不需重复装拆。脚手钢管...
Improvement of barrel mould construction In the construction of a silo at a cement factory, we adopted an improved moulding method and achieved good technical and economic results. The method is mainly to cancel the three sets of attached triangular racks and internal and external hanging baskets for conventional mold casting, and adopt ordinary 48-pin hand steel pipes and external movable lifting and hanging scaffolds assembled by snap connection. It only needs to be assembled once and does not need to be repeated. Assembly and disassembly. Foot pipe...