论文部分内容阅读
通过对3#高炉TI565主机故障分析,进行了整改的方案设计和实施,最后顺利地完成了用TI555代替TI565的工作,确保了生产的正常进行。
Through the analysis of the fault of TI565 mainframe of No.3 blast furnace, the program design and implementation of rectification were completed, and finally the work of replacing TI565 with TI555 was completed smoothly to ensure the normal production.