论文部分内容阅读
在毛主席革命路线指引下,湛江地区鹤地水库工人、干部和技术人员,坚持自力更生、土法上马、大搞技术革新,在第二溢洪道等工程上成功地使用各种滑行模板新技术,多快好省地完成了闸室主体工程的建设任务.滑行模板由钢模板、桁架、立柱导轨、提拉系统四个部分组成.面板尺寸为90×90厘米,嵌固于桁架的一侧.桁架承受模板传
Under the guidance of Chairman Mao’s revolutionary line, the workers, cadres and technicians of Crane Reservoir in Zhanjiang Prefecture have persisted in self-reliance and have launched the indigenous method and made great efforts in technological innovation. They have successfully used various new gliding template technologies in the Second Spillway Project and many more The project of building the main chamber of the sluice chamber is completed quickly and economically.The sliding template consists of four parts: steel formwork, truss, column guide and lifting system.The size of the panel is 90 × 90 centimeters, which is embedded in one side of the truss Bear the template pass