上海市轨道交通2号线东延伸段张江高科站的1号出入口采用矩形顶管法施工,该工程的始发井、接收井宽度小,且进、出洞口区域存在重大市政管线,进洞口顶管离大口径雨水管线极近,施工难度很高。结合工程实际情况,进行管线风险分析,详细介绍了顶管施工过程中的管线保护技术。监测结果表明,有针对性地选择掘进机头,制定科学的施工参数,采取精密的管线保护措施,完全能够把管线及地面沉降变形控制在安全范围内。
Shanghai Metro Line 2 East Extension Zhangjiang Hi-Tech Station entrances and exits No. 1 rectangular pipe jacking construction, the project of the starting well, receiving well width is small, and into and out of the region there is a major municipal pipeline entrance, Tube from large-caliber rainwater pipeline close to the construction of a high degree of difficulty. Combined with the actual situation of the project, the pipeline risk analysis was carried out, and the pipeline protection technology during the pipe jacking construction was introduced in detail. The monitoring results show that the selection of heading machine head, the development of scientific construction parameters, the use of sophisticated pipeline protection measures, fully able to pipeline and ground settlement control in a safe range.