鱼梁航运枢纽工程是国家“十一五”期间重点项目,是打造西江亿吨黄金水道关键项目之一,工程总投资为19.57亿元,枢纽二期坝建设期间,一期坝泄洪能力受限,汛期为抵御超标洪水,通过密切观察与监控,科学论证分析,果断决策,不拘泥于常规运行方式,创新性地利用船闸充泄水阀门来增加泄洪能力,保障了二期围堰不过水,避免了主体工程的施工工期损失近3个月,经济损失约1925万元,创造了极好的工程管理绩效,成为工程管理技术创新的亮点。
The main project during the “11th Five-Year Plan” period is one of the key projects to build a billion tons of gold waterway in Xijiang City. The total investment of the project is 1.957 billion yuan. During the construction of the second dam of the hub, the discharge capacity of the first dam Limited, the flood season to resist excessive floods, through close observation and monitoring, scientific proof analysis, decisive decision, not rigidly adhere to the conventional mode of operation, innovative use of the ship lock valve to increase flood discharge capacity, to ensure the second phase of the coffer however Water, to avoid the main project construction period of loss of nearly 3 months, the economic loss of about 19.25 million yuan, creating excellent project management performance, engineering management technology innovation highlights.