BПT-50-2型汽轮机的安装工作,是在苏联列宁格勒制造厂的代表帮助下进行的。由于这种型式汽轮机的结构不同,所以在安装方法方面,也有它的特点。以下按主要工序介绍一下我们的安装经验。一、设备清扫检查过去我们只是清扫设备上的黄干油和修理毛刺。为了提高安装质量,此次对BIIT-50-2型汽轮机还进行了下列工作:1.台板的研磨工作和过去一样,台板滑动面及底
Installation of the BПT-50-2 turbine was carried out with the help of representatives from the Leningrad plant in the Soviet Union. Because of this type of steam turbine structure is different, so the installation method, but also has its characteristics. Following the main process to introduce our installation experience. First, the equipment cleaning inspection In the past we just cleaned the equipment on the yellow dry oil and repair burrs. In order to improve the quality of the installation, the BIIT-50-2 turbine also carried out the following work: 1. Platen grinding work As in the past, the platen sliding surface and the bottom