在柳州枢纽施工改造过程中,通过对施工总体安排、铁路局运输组织、当地征地拆迁进度的深入探讨及分析,采取了先行停用既有车站中部股道,后对既有正线进行过渡的施工方案。在对铁路局运能影响最小的情况下,为新建车站股道创造了条件;从而达到站场改造与铁路局运能兼顾的双向共赢。
In the process of construction and reconstruction of Liuzhou hub, through the in-depth discussion and analysis of the overall arrangement of the construction, the transport organization of the railway administration and the progress of the local land requisition and demolition, it took the first step to deactivate the middle stock track of the existing station and then to the existing positive transition Construction program. Under the condition of having the least impact on the transportation capacity of the railway administration, the conditions for the new railway station have been created; thus achieving a two-way win-win situation of both the station reconstruction and the railway administration.