查勘规划设计20世纪50年代-2003年120世纪50年代,国家规划在金沙江上修建向家坝600万千瓦、溪洛渡1260万千瓦、白鹤滩1250万千瓦、乌东德650万千瓦4个梯级水电站。21985年,中南勘测设计研究院正式进场,开展向家坝水电站的勘测设计工作。31996年5月,中南勘测设计研究院提交向家坝工程预可行性研究报告。42002年6月,向家坝水电站经国家计委立项。52003年2月,中国长江三峡工程开发总公司成立金沙江水电开发有限公司筹建处,开始筹备向家坝、溪洛渡电站的开发,拉开了进军金沙江的序幕。
Survey planning and design 1950s - 2003 In the 1950s, the state planned to build 6 million kilowatts of Xiangjiaba, 12.6 million kilowatts of Xiluodu, 12.5 million kilowatts of Baihetan, and 4.5 million kilowatts of Wudongde four hydropower stations on the Jinsha River. In 21985, Zhongnan Investigation Design and Research Institute officially entered the site to carry out survey and design of Xiangjiaba Hydropower Station. In May 31996, Zhongnan Investigation Design and Research Institute submitted a pre-feasibility study report to Xiangjiaba Project. In June 42002, Xiangjiaba Hydropower Station was approved by the State Development Planning Commission. 52003 In February, China Three Gorges Project Development Corporation set up Jinsha River Hydropower Development Co., Ltd. Preparatory Office, began preparations for Xiangjiaba, Xiluodu hydropower development, opened the prelude to enter the Jinsha River.