我国第一座水力发电站——云南石龙坝电站,装机容量为两台240千瓦水轮发电机组共480千瓦,利用落差15米,引用流量5m~3/s,筑石砌重力溢水闸坝于滚龙坝,长55米,高2米,16孔叠木闸门,并于进水口首部设手动控制闸一道,引水明渠设于右岸,全长1478米,宽3米,深2米,23千伏高压输电线,长34公里,供电昆明。 1949年12月9日云南和平解放,在旧中国37年的石龙坝水电站,几经战乱,缺乏全
China’s first hydroelectric power station - Yunnan Shilongba Hydropower Station, installed capacity of two 240-kilowatt hydro-generating sets a total of 480 kilowatts, the use of a drop of 15 meters, the reference flow of 5m ~ 3 / s, building stone gravity overflow dam At Lunlong Dam, a 55-meter-long, 2-meter-high and 16-hole stacked wooden gate with a manual control gate at the inlet of the water intake. The diversion channel is located on the right bank of the river, with a total length of 1478 meters, a width of 3 meters and a depth of 2 meters. KV high voltage transmission line, 34 kilometers long, power supply Kunming. December 9, 1949 Yunnan peaceful liberation, 37 years in old China Shilong dam hydropower station, after several war, the lack of all