主要介绍了TRT对高炉顶压的控制及顶压测量值的优化方案。在日钢,当TRT机组不运行时,高炉顶压测量值主要通过减压阀组的开度来调节;当TRT机组投入运行,完成并网操作后,高炉缓慢关闭减压阀组,把高炉顶压逐渐转到TRT机组控制。2007年完成TRT顶压测量值优化改造之后,实现了很好的经济效益。
Mainly introduces the TRT on the blast pressure control and pressure measurement optimization program. In Japanese steel, when the TRT unit is not running, the blast pressure measurement is mainly through the opening of the pressure reducing valve group to adjust; when the TRT unit is put into operation, and the grid operation, the blast slowly shut down the valve group, the blast furnace Pressure gradually turn TRT unit control. After the completion of optimization and transformation of TRT pressure measurement in 2007, good economic benefits have been achieved.