随着以国内东方电机有限公司为主生产的9号机组的投产发电,三峡工程左岸电站的14台机组全部投产,这标志着三峡工程左岸电站的机电工程圆满地完成,比国家批准的设计工期提前了一年。同时这也标志着我国目前装机容量最大的单个电站的机电工程的成功设计、制造、安装和运行。尤其难能可贵的是,通过左岸电站大型水轮发电机组、超高压大容量升压变压器、大规模500kVGIS开关站的联合设计、合作制造、转让技术、消化吸收,我国大型水力发电和超高压输变电设备的设计制造能力,特别在巨型水轮发电机组设计和制造方面实现了跨越式的发展。
With the commencement of power generation of Unit 9, which is mainly produced by Dongfang Electric Co., Ltd., all 14 units of the Three Gorges Left Bank Power Station have been put into operation, which marks the successful completion of the electromechanical project of the left bank power plant of the Three Gorges Project more than the nationally approved design period One year in advance. At the same time, this also marks the successful design, manufacture, installation and operation of the electromechanical engineering of a single power station with the largest installed capacity in China at present. Particularly commendable is that through the joint design of large-scale hydroelectric generating set of the left bank power station, high-voltage large-capacity step-up transformer, large scale 500kV GIS switch station, cooperation in manufacturing, transfer technology, digestion and absorption, China’s large hydropower and EHV power transmission and transformation Equipment design and manufacturing capabilities, especially in the design and manufacture of giant hydro-generating units to achieve leaps and bounds.